How Is Epoxy Flooring Installed? Application in 7 Steps

How Is Epoxy Flooring Installed? Application in 7 Steps

In Brief

Epoxy flooring is installed in seven steps: assessing the floor, mechanical surface preparation, repairing cracks and voids, priming, applying the epoxy coating layer, topcoat and line marking, and curing. The stage that most determines the quality of the job is surface preparation; a coating applied to poorly prepared concrete will peel sooner or later.

How Is Epoxy Flooring Installed? Application in 7 Steps

How do you apply epoxy flooring? The short answer: the floor is assessed, the surface is mechanically prepared, damage is repaired, primer is applied, the epoxy coating layer goes down and the floor is left to cure. The long answer lies in the details that need attention at every step, because the service life of an epoxy floor depends more on the application than on the material. In this article we walk through every stage, from site survey to handover, in order.

Before installation: site survey and system selection

Every epoxy flooring installation starts with choosing the right system: we prepare a written quote from the floor area, photos of the floor and information on how it is used, and once the quote is approved, the floor is checked during the on-site survey. When choosing the system, the traffic on the floor (foot traffic, pallet jacks, forklifts, vehicles), chemical exposure, wet conditions and temperature are assessed. This information determines which system will be applied: an economical epoxy floor paint, a 2–3 mm self-leveling epoxy, a textured anti-slip epoxy for wet areas, or an anti-static epoxy for electronics manufacturing? You can find the differences between the types in our guide what is epoxy flooring.

1. Assessing the floor

Before application, three properties of the concrete are checked: soundness, moisture and cleanliness.

  • Soundness: The concrete must be at least 28 days old and its surface must not crumble like sand. If necessary, the surface pull-off strength is measured.
  • Moisture: The moisture content must measure below 4%. Where moisture rises from below the slab, a special moisture-tolerant primer is required.
  • Cleanliness: There must be no oil, paint, curing membrane or weak screed layer on the surface.

If these checks are skipped, even the best material will not deliver results. Most complaints about blistering and peeling come from skipping this stage.

2. Surface preparation

For epoxy to grip the concrete, the pores of the surface have to be opened. Diamond grinding machines or shot blasting are used for this. The process removes the weak, glossy layer on top of the concrete (the laitance) and leaves a rough, clean surface. Edges and corners are prepared with handheld grinders. The floor is then cleared of dust completely with an industrial vacuum.

Acid washing or sweeping alone is no substitute for mechanical preparation. On floors with an old coating, the old layer is removed first; sound, well-bonded old epoxy, however, can be roughened and coated over.

3. Repairs

Cracks are opened up in a V shape and filled with epoxy repair mortar. Broken joint edges, pits and voids are repaired. Oil-soaked areas are cleaned, or cut out and replaced if the oil has penetrated very deeply. Movement (expansion) joints are not covered over by the coating; they are re-cut after coating and filled with a flexible sealant. Otherwise, when the concrete moves, the coating cracks along the joint line.

4. Primer

A low-viscosity epoxy primer is worked into the concrete by roller or trowel. The primer penetrates the pores of the concrete, both creating a bonding bridge and preventing air bubbles from rising from below. Very absorbent floors may need a second coat of primer. In self-leveling and thick systems, quartz sand is broadcast onto the primer to create a key for the next layer. If the surface has irregularities, they are corrected at this stage by applying epoxy filler.

5. Coating layer

The resin and hardener are mixed with a low-speed mixer in the ratio and for the time specified by the manufacturer. Even a small error in the ratio can leave sticky, uncured patches on the surface. The mixed material must be applied within its pot life, which ranges from a few minutes to half an hour.

  • Self-leveling system: The mix is poured onto the floor, spread to the required thickness with a notched trowel and de-aerated with a spiked roller.
  • Paint system: Applied in two coats by roller, using cross passes.
  • Anti-slip system: Quartz sand is broadcast onto the wet coat; once the excess has been swept off, a seal coat is applied.
  • Metallic system: The pigmented resin is poured and the pattern is shaped by hand while it is still wet. Details are on our metallic epoxy flooring page.

At this stage the ambient temperature must be between 10–30 °C, and the floor temperature must be kept at least 3 °C above the dew point. Otherwise, whitening, dulling or tackiness will appear on the surface.

6. Topcoat and line marking

In areas exposed to sunlight, or on decorative floors that need scratch resistance, a UV-resistant polyurethane topcoat is applied over the epoxy body coat. We explain how the two materials work together in our article epoxy vs. polyurethane flooring. On parking garage and factory floors, parking, directional and pedestrian walkway lines are also marked at this stage.

7. Curing and handover

  • 24 hours: It can be walked on.
  • 2–3 days: It can be opened to light loads and pallet jack traffic.
  • 7 days: It reaches full mechanical and chemical resistance and is ready for forklifts and chemical contact.

These times apply at 20 °C and are longer in cold weather. For details, see our article how long does epoxy flooring take to cure. On anti-static floors, resistance is measured before handover and the results are documented in a report.

How long does epoxy flooring installation take?

For a medium-sized area (a few hundred square meters), surface preparation, repairs, priming and coating are usually completed in 3–5 working days, with the curing time added on top. In large facilities the work can be divided into zones and carried out in phases so that production does not have to stop. On our warehouse, hospital and food processing pages we also explain how installation is planned while the facility stays in operation.

The most common epoxy flooring application mistakes

  • Starting the application without measuring moisture.
  • Coating the surface after only sweeping it, without grinding.
  • Mixing the components in the wrong ratio or not thoroughly enough.
  • Applying the material thinner than it should be.
  • Covering expansion joints over with the coating.
  • Working in cold, damp conditions without checking the dew point.
  • Opening the floor to loads and water before curing is complete.

DIY or professional installation?

In a small home garage, you can apply epoxy with a ready-made kit; however, without a diamond grinder, a moisture meter and experience, the risk of blistering is high. In industrial areas, surface preparation, thickness control and curing conditions all call for professional equipment. To protect your floor for many years after installation, take a look at our epoxy floor maintenance and cleaning guide.

To work out the right system and installation schedule for your space together, you can request a quote.

Epoxy Systems and Sectors Mentioned in This Article

All Services

Related Articles

All Articles

Turn your floor into a durable, hygienic and attractive surface.

Our priority is

Tell us about your project, and together we will pin down the right epoxy system for your floor, the application time and our quote.

Get a Quote

5-year workmanship and 10-year product warranty. We respond to all requests within 24 hours. We work in all 81 provinces.